Investment
Planning a 500 million yen investment in the extraction and sales business.
03 / Kaga City, Ishikawa / Resources, investment, site reuse
A plan to invest in extracting and selling soil and sand, then use the extraction site for the next business after three years.
KAGAKaga City, Ishikawa

500million yen
Investment in the extraction and sales business planned.
3years
Planned sales of 300,000 m³ a year, 900,000 m³ in total.
900,000m³
Planned sales over three years; part of the estimated extractable volume.
STEP 01 / First three years
Extracting and selling soil and sand
300,000 m³ a year × 3 years = 900,000 m³
Considering use of the site after three years
Concept diagram of the project stages | Not a layout of facilities or the extraction area.
Planning a 500 million yen investment in the extraction and sales business.
Planned sales of 300,000 m³ a year, 900,000 m³ in total.
Considering a plant or a final disposal site for used solar panels.
03 / Kaga City, Ishikawa / Business plan
In talks with the supplier, checking the contract
About 60,000 tsubo. Of the 20 m below ground, excluding 1 m of topsoil, a 19 m sand layer is assumed.
About 3.7 to 3.8 million m³; area × depth gives roughly 3.77 million m³. To be confirmed taking geology and slopes into account.
300,000 m³ a year for three years, for the Kaga Onsen Station area development and Katayamazu IC-related works. The sand buyers will provide the dump trucks.
Investment of 500 million yen. The operator says a purchase contract with Kaga City is in place; the contract, unit prices and payment terms have not yet been checked.
Considering a plant business or a final disposal site for used solar panels. Location, permits and coordination with the extraction schedule need to be worked out.
If a plant is introduced on the site, moringa cultivation, biochar and a carbon credit business will also be planned.
Current progress
Through an introduction by Fu-chan Net, we are in talks with a local company that supplies landfill soil for the city's development plan south of Kaga Onsen. We were told it already has a contract with Kaga City and are checking the details. We are considering a 500 million yen investment and use of the site after three years.
The planned sales of 900,000 m³ over three years are only part of the estimated extractable volume. We will set out the contract form of the investment, profit sharing and terms for recovering the funds.
We have received the quarrying business registration application documents. These do not prove that registration is complete.